  • THE PROJECT:

    McCarthy Building Company, Inc. was given the overwhelming task to complete the 378,000 sq. ft. medical center in just 19 months. Since this was the first Banner project for McCarthy, it was important that the right asphalt company was contracted to make sure that the project started off on or ahead of schedule.

  • THE ACE SOLUTION:

    Besides being low bidder on this project, we provided the most complete bid package of all competitors to McCarthy for the scope of work. This included the removal and disposal of existing asphalt and concrete, clearing and grubbing the site, balancing the grade, stockpiling excess material to limit unnecessary import, fine grading the curb grade, flatwork grade and landscape areas, paving up to 4-inch deep asphalt on 12-inch deep compacted aggregate base course, and adjusting necessary utilities. Final touches included striping 850 standard stalls, 30 handicap stalls, 26 directional arrows, 1 helipad, and placement of required wheel stops and signage. Our performance enabled McCarthy to fulfill their obligation to Banner within the tight deadline.

RELATED PROJECTS

Notable Projects with Customer: Maricopa High School, Perryville Prison, Brogan Maintenance Center, Broadmor Elementary School, Chandler High School, Chaparral High School, Promenade, Val Vista Water Treatment Facility

Quick Facts/Technical Specs: ABC Tons: 31,404
Asphalt Tons: 10,657
Number of Parking Stalls: 880
Customized markings: Helipad striping

Paving, Earthwork, Demolition, Striping & Markings